Designing training is as much of an art as it is a science. However, that doesn’t mean we should abandon the act of trying to figure out how long it takes to develop an hour of training. Scientific measures and standards can be applied at least as rough guidelines. With some type of standard, it becomes possible to gain a general idea of how much time a training project might take. While many may argue about using “one hour of training” as a measuring stick because of the difficulty of determining exactly what one hour means, it is a common term and has some traction with managers trying to plan resources. It’s not perfect, but it is a way of making comparisons.

 

Too often when asked about developing training, internal and external clients hear “it depends.” While this is true, that answer doesn’t help when budgeting time or resources. What someone really wants as a response to that question is a realistic number as to how long it will take to develop one hour of training. Or, at the very least, they would like a range of numbers so some type of planning can be done.

 

Here are the results from a survey we developed in a rough attempt to align credible numbers for use in estimating work based on delivery method and complexity of interactivity. We also review the key factors that can cause delays and contribute to that famous “it depends” answer.

Demographics

 

To conduct the study, we reached out to our peers in the industry to gather data and had 47 respondents, of which 83 percent have a degree related to the field of instructional technology/design. Other points to note:

  • the majority (61 percent) of our respondents performed both the role of the designer and developer in their job tasks
  • the majority (75 percent) of the materials that respondents worked with were raw; meaning they came from Subject Matter Experts (SMEs) and/or their own research
  • the two dominate methods for estimating development hours were estimates based on similar projects (36 percent) and the use of variables (31 percent) such as expertise, project-related work, environmental factors, and so forth
  • internal customers (41 percent) and vendors (39 percent) made up the majority of respondents. Independent consultants (11 percent) rounded out the top three
  • several industries were also noted and a breakdown can be reviewed in the chart below.

 

Results

 

The mainstay of our study covered various development tools and the levels of interactivity based on the ADDIE model. The study did not include time estimates for summative evaluation, only formative. One set of questions covered the use of templates within development. The survey indicated that Microsoft Word and PowerPoint were the predominant development software as 71.7 percent of all respondents use these to develop instruction. Adobe Flash (56.5 percent) and Captivate (50 percent) were next in line as leading software development tools with LMS-based tools (26.1 percent) following them. Other tools such as Articulate (19.6 percent), Lectora (15.2 percent), and WebEx Presentation Studio (10.9 percent), though not as popular, still had a number of respondents.

 

The chart below indicates the numbers from our most recent survey and the numbers from the survey and data gathered in 2003. Respondents only provided numbers to the methods that they have used. It is interesting to note that in six of the areas, the time estimates actually increased. Note: NA is listed in some of the responses for 2003 because these are new questions in 2009.

 

Type of Training per 1 hour

Low Hours

Per hour of Instruction

(2009)

High Hours

Per Hour of Instruction

(2009)

Low Hours

Per hour of Instruction

(2003)

High Hours

Per Hour of Instruction

(2003)

Stand-up training (classroom)

43

185

20

70

Self-instructional print

40

93

80

125

Instructor-led, Web-based training delivery (using software such as Centra, Adobe Connect, or WebEx-two-way live audio with PowerPoint)

49

89

30

80

E-learning Developed without a Template

Text-only; limited interactivity; no animations

93

152

100

150

Moderate interactivity; limited animations

122

186

250

400

High interactivity; multiple animations

154

243

400

600

E-learning Developed within a Template

Limited interactivity; no animations (using software such as Lectora, Captivate, ToolBook, TrainerSoft)

118

365

40

100

Moderate interactivity; limited animations (using software such as Lectora, Captivate, ToolBook, TrainerSoft)

90

240

150

200

High interactivity; multiple animations (using software such as Lectora, Captivate, ToolBook, TrainerSoft)

136

324

60

300

Limited interactivity; no animations (using software such as Articulate)

73

116

NA

NA

Moderate interactivity; limited animations (using software such as Articulate)

97

154

NA

NA

High interactivity; multiple animations (using software such as Articulate)

132

214

NA

NA

Simulations

Equipment or hardware (equipment emulation)

949

1743

600

1000

Softskills (sales, leadership, ethics, diversity, etc.)

320

731

NA

NA

 

Factors that effect development time

 

So why did some times increase and why does it take so long to develop instruction in the first place? (by develop we mean the ADDIE process). This leads us to our next question where would we be without our clients and SME’s? Apparently developing instruction in a lot less time. Now this is not an attempt to knock clients SME’s (we love them); however there were some clear trends in the qualitative responses indicating three main issues impacting the time to develop instruction and they primarily stem from the client; scope of work, technology, and review time.

 

It was noted in the qualitative comments that client project managers, SME(s), and their organizations, did not have a firm grasp on their own needs. This can be the cause of major time delays. Expectations of what the project would look like as a finished product causes delays as does the desire to add additional content at the last minute. Within the scope of work there were also sub-factors, such as

  • lack of understanding of one’s responsibility to project; which included not allotting enough time to review work, SME unavailability, provision of materials in a timely manner
  • organizational changes; changes impacting either resources for the project or the overall project
  • incompatible technology and/or lack of knowledge of a technology. It was noted several times that the clients’ technology was incompatible and/or there was a learning curve to using the new tools. To a lesser degree it was also mentioned that software quirks also lent to development time being impacted.

 

So one of the ways to reduce the overall time to develop one hour of training is to streamline how you interact with the client. Finding methods to help the client work more effectively and understand the learning technologies would help to reduce the overall time investment.

 

Reducing the factors

We don’t want to leave this article hanging on the negative attributes of developing an hour of training, so here are some ways to minimize some of these factors to reduce the time. Try incorporating a few of these best practices into your next project or better yet consider building them right into your process to speed up your projects.

  • Conduct an orientation for the SME and key project stakeholders. During the time that you kick off the project and discuss roles and responsibilities include informational take-aways to reinforce main points reviewed during the meeting. For example, providing a SME with a description of their responsibilities and what that looks like from a time perspective (how many hours should they set aside) can allow them to better prioritize and allocate their time for the project along with all of their other commitments.

  • Communicate, communicate, communicate. We may not want to do it, but more communication is effective for keeping project stakeholders current and familiar with the project and its present status and issues. The additional communications can also be leveraged to remind individuals of upcoming tasks and milestones. Help the SME or client prioritize by continually communicating to them their dea dlines.

  • Be prepared to help implement change management. If your client’s organization just re-structured— they are probably dealing with their own internal change management processes. Create and implement your own change management process for these types of occurrences to ensure the project doesn’t lose ground. For example, if you are losing two SME’s from your project and gaining two new ones; have you developed a change management process to ensure that the two leaving are off-boarded and that you have everything you need from them to onboard the two new SME’s?

  • Assess and develop a technology onboarding process. If you have identified that there is the potential for technology complications, build a parallel process that starts along with the rest of the project but handles identifying all concerns around the technology component of the project. Once the analysis is done develop a plan that resolves each issue identified in tandem with the other project goals to ensure the technology will work when its needed and that those key project members who must use the technology have been building their technology competency during the development of the training.

 

To be sure, “one hour of training” is not an absolute but can serve as a guide for managing projects that require the creation of instruction. In the current marketplace, the pressure is on to meet or exceed standards in terms of instructional development. Methods to reduce the overall time required are to ensure that the client-vendor (internally or externally vended) process accounts for the true breadth and depth of the client’s expectations, the project stakeholders comprehend their role and responsibilities and the value of their contributions, and technological risk factors are considered. Once these factors are identified and addressed, the question “how long does it take to develop one hour of training” can continually have a shorter and shorter answer.

About the Author

Karl Kapp, Ed.D. is a professor of instructional design and technology at Commonwealth University, Bloomsburg Campus. He is an internationally recognized expert, consultant, and instructor on the convergence of learning, technology, and business. Follow him on LinkedIn at https://www.linkedin.com/in/karlkapp and email at [email protected].

About the Author

Robyn A. Defelice, PhD is a consultant, author, and presenter with over 20 years in the L&D field. She is the co-author of Microlearning: Short and Sweet and has been researching How Long Does it Take to Develop Training for over a decade.

Robyn’s passion comes from working with L&D leadership and teams and supports them in taking their seat at the decision-making table. She strives to empower L&D professionals using her adventures in meeting client challenges, from corporate to manufacturing, government to higher education, and non-profits to startups.

She enjoys presenting to ATD chapters and sharing on her three favorite topics: problem-solving capabilities, microlearning, and learning operations. She is also currently serving as the VP of Programs for ATD Central Pennsylvania.

6 Comments
Sign In to Post a Comment
I am curious whether the majority of ID's are still using PowerPoint? Current slide deck tools such as Canva have AI and templates that make it possible to create training decks in 90% less time and are more visually appealing. The end product can be imported into PowerPoint, but I rarely do that. Presentations can be made directly from Canva and even recorded to provide a video.
Sorry! Something went wrong on our end. Please try again later.
Good day,
I need recent information about the man hours needed to develop for A to Z one hour of instruction. Could you please help me on this matter?
Regards,
Hussain
Hi Hussein, I am not following what you are asking. Could you clarify?
Sorry! Something went wrong on our end. Please try again later.
Good day.
Thank you for your reply. I know that the research is focused in one UNIT that is less than one hour. So, in this case, how much are the man hours to develop material for that UNIT? Thank you.
Sorry! Something went wrong on our end. Please try again later.
Hello - This update was published in January: https://www.td.org/insights/how-long-does-it-take-to-develop-training-new-question-new-answers
However, the research is no longer focused on 1-hour of training.
Sorry! Something went wrong on our end. Please try again later.
I second that. I'd like to see how these figures have changed within the last 5 years.